Air sealing · Penticton, BC

Air sealing in Penticton.

Penticton is one of the Okanagan municipalities that requires a mid-construction airtightness test, not just a final one. Here is what that means for your schedule.

Short answer

The City of Penticton requires Part 9 homes to meet at least Step 3 of the BC Energy Step Code, with airtightness testing at both mid-construction and completion (Building Bylaw 2021-21). Okanagan AeroBarrier seals Penticton and South Okanagan builds to a measured ACH50 target, ideally around the mid-construction test.

Two tests, not one

Penticton's Green Build requirements say airtightness testing at mid-construction and at completion is a requirement of the Step Code in Penticton, adopted through Building Bylaw 2021-21. Part 9 homes must reach at least Step 3.

That mid-construction test is the best thing that can happen to your schedule, because it is exactly when a seal is cheapest and easiest. Book the seal right after it (or right before, if you would rather the mid-construction number already be a pass), and the final test is not a surprise. How the tests fit together.

Scheduling South Okanagan work

I am Kelowna-based and batch Penticton, Summerland and Naramata work, so give me your mid-construction date as early as you can. Rescue calls after a failed test get fitted in as fast as the schedule allows. Failed blower door test.

Written by Sebastian Motora, owner-operator. Last reviewed October 7, 2026.

Penticton air sealing: common questions

Does Penticton require a mid-construction blower door test?

Yes. Penticton requires airtightness testing at mid-construction and at completion for Step Code homes (Building Bylaw 2021-21). Your energy advisor runs both.

Do you cover Summerland and Naramata?

Yes, batched with Penticton work. See the service area.

Building in Penticton? Send me the project.

Plans, target step, stage and timeline. You talk to the owner who runs the seal, usually the same day.